文章就龙滩水轮机转轮的水力设计、模型试验、转轮结构设计、转轮工地制造及转轮的最终验收,进行评述并提出一些建议。
The thesis comments on the hydraulic design, the model test, the runner structure design, the runner field fabrication and the acceptance check. Some proposals are put forward also.
简要介绍了飞来峡水电站水轮机的模型验收试验的情况及结果。
This paper presents the turbine model acceptance test and the test results of Feilaixia hydropower station.
岩滩水电站水轮机性能采用模型验收试验方式验收。其全模拟模型最高效率达到92%。
Model acceptance test is applied to accept Yantan turbine performances. The model efficiency maximum is 92 percent in the completion of similar prototype.
岩滩水电站水轮机性能采用模型验收试验方式验收。其全模拟模型最高效率达到92%。
Model acceptance test is applied to accept Yantan turbine performances. The model efficiency maximum is 92 percent in the completion of similar prototype.