Hydraulic fracturing in earth core rockfill dam is a key problem which is unsolved and is given an universal attention in engineering field.
土质心墙坝的水力劈裂问题一直是工程界普遍关注又亟待解决的关键问题。
It is assuredly helpful to well know these characteristics for either proper design of rockfill dam with bituminous concrete core, or reasonable construction.
全面掌握这些特征,无论对沥青混凝土心墙堆石坝的正确设计,还是合理施工,无疑都是有帮助的。
Finally, the shear strength reduction technique is used to analyze the seismic stability of Nuo Zhadu core wall type rockfill Dam and Chang Heba core wall type rockfill Dam in FEM.
最后,采用有限元强度折减技术分析了糯扎渡心墙堆石坝及长河坝心墙堆石坝上下游坝坡的抗震稳定性。
Maopingxi high rockfill dam is the accessorial dam of Three Gorges Project (TGP), which is also the highest rockfill dam with asphalt concrete core in China.
茅坪溪防护坝是三峡工程的副坝,也是目前中国最高的沥青混凝土心墙坝。
These results can be referenced to the plan of water level procedures on the dam; and the behaviors of high rockfill dam with asphalt concrete core under high water head are studied.
研究结果可供大坝蓄水计划参考,并为高水头下高沥青混凝土心墙坝的运行提供一定的参考。
The deformation properties of core gravelly soil of the Nuozhadu high rockfill dam are studied by using medium-scale triaxial tests and the field loading tests.
采用室内中型三轴试验和现场碾压载荷试验对糯扎渡高心墙堆石坝心墙砾石土料的变形特性进行了研究。
The calculation and analysis of the core type rockfill dam of Lubuge Hydropower Station are conducted by the programs of total stress method and effective stress method.
鲁布革水电站心墙堆石坝采用总应力法和有效应力法计算程序进行计算和分析。
The major dam of Nierji water project is an earth- rockfill dam with asphalt concrete core.
尼尔基工程主坝为沥青混凝土心墙土石坝,主坝工程施工采用两期导流方式。
Core wall rockfill dam is one of the representative types of the Shuibuya Project on the Qingjiang River.
心墙堆石坝是清江水布垭水利枢纽的代表性坝型之一。
This rolling construction technology of asphalt concrete core wall in Maopingxi earth and rockfill dam of TGP was the first application in China.
三峡茅坪溪防护土石坝沥青混凝土心墙骑缝碾压施工工艺为国内首创的施工方法。
Asphalt concrete core-wall rockfill dam is one of the main types of earth-rock dam.
沥青混凝土心墙堆石坝是土石坝的主要坝型之一。
The new dam consists of an earth core rockfill embankment and a concrete transition at the left abutment.
新建坝包括一座土质心墙堆石堤坝和一个位于左坝肩的混凝土过渡带。
The research status of hydraulic fracturing in core of earth-rockfill dam is briefly reviewed, and the mechanisms, the conditions and the influence factors of hydraulic fracturing are induced.
简要评述了国内外关于土石坝心墙水力劈裂的研究现状,归纳了土石坝心墙水力劈裂在发生机理、发生条件和影响因素等方面的研究成果。
The changes of pore water pressure in the core wall of earth - rockfill dam are generally delayed relating to that of the reservoir level.
土石坝心墙中孔隙水压力的变化常滞后于库水位的升降。
The major dam of Nierji water project is an earth - rockfill dam with asphalt concrete core. The construction diversion is used two stages.
尼尔基工程主坝为沥青混凝土心墙土石坝,主坝工程施工采用两期导流方式。
According to comprehensive analysis, it is thought that hydraulic fracturing in core of earth-rockfill dam is hard to occur.
最后通过综合分析,认为在实际工程中,土石坝心墙很难发生水力劈裂。
According to comprehensive analysis, it is thought that hydraulic fracturing in core of earth-rockfill dam is hard to occur.
最后通过综合分析,认为在实际工程中,土石坝心墙很难发生水力劈裂。