If the Contractor's priced proposals for an acceleration are accepted by the Employer, they are incorporated in the Contract price and treated as a Variation.
如果业主接受了承包人为赶工提出的价格建议,那么这个价格将构成合同价格,并视做一个工程变更。
If the Contractor's priced proposals for an acceleration are accepted by the Employer, they are incorporated in the Contract price and treated as a Variation.
如果业主接受了承包人为赶工提出的价格建议,那么这个价格将构成合同价格,并视做一个工程变更。