The lining structure with concentrated copper cooling plate-stave combined system for the large-scale blast furnace is the important guarantee of 18 ~ 20 campaign life.
大型高炉的密集式铜冷却板与冷却壁结合的炉衬结构是使高炉寿命达到18 ~20年的一项重要保证措施。
In the forward to 21 century, the blast furnace technology will be improved in several fields: 1. injection coal and decrease coke rate, 2. Extending of BF campaign life.
面向21世纪,高炉技术将在以下几个方面等到得到了明显的进步:1 .大量喷煤降低焦比。
The campaign life problem confronted with intensified blast furnace and their main causes are analysed in this paper.
本文总结了我国高炉寿命方面存在的问题并分析了产生这些问题的主要原因。
No. 8 Blast Furnace design and its body's cool structure adopt the unique technology to guarantee the high yield, high-quality, low consumption and long campaign life of B.
柳钢8号高炉炉体冷却结构采用独特的工艺技术,保证了高炉的高产、优质、低耗、长寿。
No. 8 Blast Furnace design and its body's cool structure adopt the unique technology to guarantee the high yield, high-quality, low consumption and long campaign life of B.
柳钢8号高炉炉体冷却结构采用独特的工艺技术,保证了高炉的高产、优质、低耗、长寿。